2012-12-11 - 5502 - Service Request - Mateiral 10695615 Program Consolidation #ProductionBreakFix #purchaserequisitions
5502 - Service Request - Mateiral 10695615 Program Consolidation
Summary Description
Material 10695615 Program Consolidation.
Admin Info
Purpose
|
Material 10695615 Program Consolidation
|
Requested by
|
Jeff Mau
|
Issue Date
|
12-11-2012
|
Resolved by
|
Laxman
|
Resolved Date
|
12-21-2012
|
Document Status
|
Complete
|
Detailed Description
(Include Screen Shots if required )
A program material 10695615 is set up to be MRP with six month to prevent multiple reqs but on a recent PO it has two different line items. Why?
Analysis and Recommendations
(Include Screen Shots if required)
Understand that there are two purchase reqs are created through MRP on 08/30/2012. For the first purchase requisition requirement date is within six months from the date 08/30/2012 and for second requisition requirement date is above six months. So two separate purchase requisitions are created since lot size is six months. Then purchase order is created with this requisitions
and later on delivery date is changed for both items as same date which is leading to confusion.
Resolution
Client understand the logic behind creation of two separate requisitions even though lot size is six months.
Release Information